264's testing continues...

264’s testing continues…

The extensive testing of Sheffield 264 continues, the aim being to carry out all remedial work before the tram re-enters Road 1 for completion of its paintwork.  We are also having new corner windscreens manufactured (at eye watering cost!) which will replace the temporary ones fitted at the moment.

Below: The tram made its first full laps of the site today and, following attention to a number of small jobs, will begin two solid days of testing to allow it to bed in.  It can then receive the equivalent of a C exam before painting commences.  It is seen here in the Town, for the first time in a number of years (though not so many as it has been out of passenger service for, as it was kept in operational condition for some time after it was taken out of service).

IMG_2692 IMG_2693

Below: Testing it on the highest section of the overhead, outside the Bank and Masonic Hall – seen here looking across to the rapidly developing Chemist & Photographers building (see the Beamish Buildings Blog for more on this: https://beamishbuildings.wordpress.com/ )

IMG_2697 edit

Below: In order to install the resistances, the panels on the platforms had to be painted to finished standard, including full lining out on one of the waist panels, seen here as a peek at what the finished livery will look like when complete…

IMG_2698

Below: Les at the helm as 264 heads from Pockerley towards the Town.  The rather wider view is the result of not having the staircases fitted yet!

IMG_2709 edit IMG_2719

Below: A team shot of the Beamish Tram Group volunteers, Pete, Mel and Les, who have worked alongside the staff to bring about the very rapid assembly and testing of 264.  The quality of ride on 264 is universally appreciated and will be something for visitors to enjoy next spring when it re-enters service at Beamish.  This will be something of an ‘itch scratched’, as when I arrived in 2004 the tram had already been withdrawn and attempts made to raise a substantial sum to have it re-built.  This wore on for years before, with the RHEC up and running and it clear that there would be no grants forthcoming to overhaul 264, the decision was made to tackle it in-house.  This has worked very well, and whilst the cost is still substantial (and would buy a very cheap house in these parts, and that excludes the labour costs or equivalent volunteer hours), we have something with which the team can be very pleased.

IMG_2715 edit

So, what’s next?!  Well, we have Gateshead 10’s new tyres on order and plan to have this dismantled in Jan/Feb to enable dispatch of the wheelsets for the tyres to be fitted (at the Ffestiniog Railway).  Meanwhile, the bogies will receive the ‘standard’ overhaul which we are becoming quite accustomed to now, with motors sent out for refurbishment.  The air brake system also needs fully overhauling and again components will go out to specialists for this work to be completed.  There is some attention required to the body, a new set of doors to be made and numerous other jobs to tackle before a full repaint into Gateshead livery – initially without the advertising boards, but these will be added fairly soon afterwards.  That will utilise the bulk of the budget for 2016/2017 and the following allocation will enable Blackpool 31 to be re-tyred.  As the rest of that tram is in good condition, then we may look at another project that same year (or at least begin a project), but we will also be anticipating work on the bus fleet at that stage too, so that may be a factor at that time.  There are also Gateshead 52 and Sheffield 513’s future prospects to consider too.  As ever, watch this space…